PS-003
Verified DISCOM reliability reporting
उदाहरण: अनुसन्धानसाझा
Supply interruption data is self-reported and inconsistent across DISCOMs.
- Owner
- Mission Lead — Climate, Energy & Water
- Baseline
- Self-reported SAIDI, no third-party audit
- Target
- Third-party verified SAIDI/SAIFI for all DISCOMs
- Sample dates
- Y1 Q1 → Y2 Q4
- Est. / actual
- ₹80 cr / ₹4 cr
- KPI
- cew-supply-interruption
- Priority
- 5 / 100
Depends on: Smart-meter data access agreements; State regulator consent
Risks: DISCOM resistance to disclosure
Y1 Q1 — Sample schedule: verification protocol drafted in Y1 Q1 and sent for expert review.
PS-004
Airshed pollution management (10 cities)
उदाहरण: अनुसन्धानसाझा
City-level plans ignore cross-boundary sources; exposure not tracked at population level.
- Owner
- Mission Lead — Climate, Energy & Water
- Baseline
- 50.6 µg/m³ annual avg PM2.5, 2024 (IQAir)
- Target
- Airshed plans with quarterly exposure reporting
- Sample dates
- Y1 Q2 → Y3 Q4
- Est. / actual
- ₹650 cr / ₹12 cr
- KPI
- cew-pm25-exposure
- Priority
- 2 / 100
Depends on: Inter-state coordination mechanism; Monitor procurement
Risks: Source attribution disputes between states; Seasonal confounding
Y1 Q2 — Sample schedule: public consultation would run for six weeks in Y1 Q2.
PS-014
Groundwater recharge with metered outcomes (20 blocks)
उदाहरण: ढिलोराज्य
Recharge structures are built without measuring aquifer response.
- Owner
- Mission Lead — Climate, Energy & Water
- Baseline
- Structures counted, not outcomes
- Target
- Metered water-table response in 20 blocks
- Sample dates
- Y1 Q1 → Y2 Q2
- Est. / actual
- ₹90 cr / ₹31 cr
- KPI
- Water-table change vs. control blocks
- Priority
- 2 / 100
Depends on: Piezometer network; CGWB collaboration
Risks: Monsoon variability masks effect
Y1 Q2 — Sample schedule (showing a slip): piezometer procurement delayed four months; design revised to add control blocks.